Strip Out Package for HMO Conversion in Stafford

November 2, 2026
A worker removing plaster from a wall on a construction site

Strip Out Package for HMO Conversion in Stafford

Overview

Sixtowns Waste recently completed a strip out package in Stafford for a builder converting a large residential property into a HMO.

The original scope was relatively straightforward, but once works began, the job developed into a larger package of internal strip out and clearance works.

Despite the scope increasing and first fix trades already being on site, the works were completed on time and the overall programme was not delayed.

This project is a good example of how strip out works need to be managed properly when plans change, trades overlap and the site still needs to keep moving.


A worker removing plaster from a wall

Project Details

Client: Builder
Location: Stafford
Project type: Strip out package
Sector: Residential refurbishment
End use: HMO conversion
Outcome: Completed on time with no delay to the wider programme


A srtipped out bathroom

The Brief

The property was being converted into a HMO, and the builder needed selected areas stripped out before the next stages of refurbishment could continue.

The original scope included:

• Removing the kitchen
• Removing the bathroom
• Taking up floor coverings
• Soft stripping 2 bedrooms

This would have created a clearer starting point for the refurbishment and allowed follow-on trades to continue with their work.

However, once the project started, the scope increased.


A kitchen after the fitted units have been removed

Scope Changes During the Project

As the works progressed, additional areas were added to the package.

The expanded scope included:

• Taking all external walls back to brick
• Clearing the front garden
• Clearing the rear garden
• Removing hardwood flooring from the living room
• Managing the additional waste generated from the extra works

Scope changes are common on refurbishment projects, especially once a building starts to open up and the client gets a clearer view of what is required.

The key is making sure the extra work is managed without disrupting the rest of the programme.


A construction worker removing constrution waste from a building site.

Working Around First Fix Trades

The timing on this job was slightly unusual.

Normally, we would complete the strip out before first fix trades begin. On this project, the first fix trades were already on site, which meant we had to work around them.

That required careful planning and site control.

Our team had to make sure that:

• Work areas were kept clear
• Waste was managed properly
• Strip out works did not block access
• Other trades were not slowed down
• The additional scope was completed around existing commitments
• Communication stayed clear throughout

This type of project requires more than simply removing materials. It needs coordination, awareness and flexibility so the wider job can continue moving.


A room that has been taken back to brick

The Work Carried Out

Our team completed the agreed strip out works and the additional scope added during the project.

The work included:

• Kitchen strip out
• Bathroom strip out
• Floor covering removal
• Soft strip works to bedrooms
• External walls taken back to brick
• Hardwood flooring removed from the living room
• Front and rear garden clearances
• Waste removal from the agreed works

The site was kept organised throughout so the builder and other trades could continue working without unnecessary disruption.


A construction worker loading rubble into a rubble bag.

Waste Management and Site Control

As the scope grew, so did the volume and variety of waste.

Waste materials were removed from site as the job progressed to keep working areas clear and reduce disruption to the trades on site.

Maintaining good site control was particularly important because the property was already active with other contractors.

A clean and organised site helps reduce delays, improves access and makes it easier for everyone to complete their part of the project safely and efficiently.


A demolition operative removing flooring

The Outcome

The strip out package was completed on time and the wider programme was not delayed.

Despite the increased scope, overlapping trades and the need to fit the final sections around other committed projects, the work was completed without causing issues for the builder.

By the end of the package, the property was clearer, more open and better prepared for the next stage of the HMO conversion.

The project helped:

• Open up the building for refurbishment
• Remove unwanted materials and finishes
• Prepare walls and rooms for follow-on trades
• Clear external areas around the property
• Keep the wider programme moving
• Avoid delays despite the changing scope


A living room taken back to brick, with the first fix electrics installed

Why This Project Matters

Not every project follows the original plan.

The scope can grow.
The sequence can change.
Other trades may already be on site.
The programme still needs to keep moving.

This Stafford project shows the importance of clear communication, flexibility and proper site control during strip out works.

For builders, developers and property investors, having a strip out contractor who can adapt without slowing the job down can make a real difference to the success of a refurbishment project.


A before & after pic showing some tree removals.

Supporting HMO Conversions and Refurbishment Projects

Sixtowns Waste supports builders, developers, landlords and property investors with strip outs, site clearances and house clearances across Stafford, Stoke-on-Trent, Staffordshire and Cheshire.

Our work helps prepare properties and sites for refurbishment, redevelopment and construction.

Whether you need a property stripped out before refurbishment, a site cleared before works begin or waste removed during a live project, we can help create a clean, safe and workable starting point.

Connect With Us

Ready to Get Your Site or Property Moving?

Contact us today for a tailored clearance or enabling works quote, designed to prepare your site for the next stage quickly, safely and compliantly.

Scroll to Top

Get early case studies, industry news and local business wins, straight to your inbox.