Barn Demolition Project in Ipstones for Local Farmer

September 14, 2026
An unsafe barn scheduled for demolition

Overview

We recently completed a barn demolition project in Ipstones for a local farmer, preparing the site for future use.

The structure was a timber framed barn with asbestos roofing and cladding, which required careful planning and a controlled approach before any demolition work could begin.


The Challenge

The presence of asbestos meant the project needed to be handled in a specific sequence to ensure everything was carried out safely and in line with regulations.

At the same time, the customer had clear instructions on what should be retained and what should be removed.

This required a selective demolition approach rather than a full clearance.


The Work Carried Out

Our team completed the demolition over a couple of days, starting with the safe removal of hazardous materials.

This included:

• Removing and disposing of asbestos roofing and cladding
• Dismantling the timber frame of the barn
• Excavating and removing structural posts from the ground
• Clearing waste and debris from site

Once the hazardous materials were dealt with, the remaining structure was dismantled in a controlled and efficient way.


A Controlled Demolition Approach

This project was not a full removal.

At the customer’s request:

• Metal posts were left in place
• The timber frame was retained for reuse

Working in this way allowed the client to keep materials they needed, while still achieving the required site clearance.


Programme

The full demolition and clearance was completed within a couple of days.

Efficient planning and sequencing meant the job was completed quickly while maintaining safety and compliance throughout.


The Outcome

With the barn safely dismantled and asbestos removed, the site is now clear and ready for its next use.

By handling the hazardous materials first and following a structured demolition process, the project was completed without delays or complications.


Supporting Demolition and Site Preparation in Staffordshire

Projects like this are a key part of the pre construction phase, particularly in rural and agricultural settings.

From controlled demolition to site clearance, preparing land and structures properly ensures the next stage can move forward safely and efficiently.

If you need demolition or site clearance in Ipstones, Stoke-on-Trent or the surrounding areas, Sixtowns Waste can help prepare your site for the next phase.

A farmers barn in the Stafordshire Moorlands
An asbestos containing barn waiting to be demolished
A demolished barn on a farm site
Demolition contractors clearing a work site
A cleared site post barn demolition

Connect With Us

Ready to Get Your Site or Property Moving?

Contact us today for a tailored clearance or enabling works quote, designed to prepare your site for the next stage quickly, safely and compliantly.

Scroll to Top

Get early case studies, industry news and local business wins, straight to your inbox.